|




| |
|
Daniel Adamson News
2007
Most recent news
appears first. |
|
DECEMBER 01
WEB MASTER OFF LINE
Please note that your web
master is likely to be off line for a period of time (to be determined
by British Telecom) commencing December 10.
This is due my phone line
being moved over to my new address. However, BT claim they have to move
the line before processing my broadband activation order.
I have been told that
broadband activation could take up to 10 working days to arrange. That
then leaves things very close to the Christmas holiday period and there
is obvious potential for things to be somewhat drawn out.
I, therefore, request that
no web site or correspondence for The Tow Line is sent via email after
December 08 until further notice.
I will announce on the web
site when I am back in communication!
THE TOW LINE - Edition 14
Apologies for delay in
completing the November edition of "The Tow Line", however, domestic
duties in connection with my move delayed completion. However, edition
14 is now completed in draft form and should be with you in the near
future.
- John H. Luxton |
|
IMPROVING THE LIGHTING
When we started this project one of the
problems was to get some sort of lighting into all the compartments to
allow the working party members to work in safety.
The existing lighting on board could not
be used because the wiring was in such a bad state, The solution was to
use 110v temporary lighting, this had two advantages, 110v is a safe
working voltage and necklaces of 110v/100w lamps are readily available.
We begged, borrowed and found some in skips and eventually had enough to
light our way throughout the vessel.
While this lighting did the job, it also
uses a lot of power and we were finding that we could not fully light
all the compartments and run 110v power tools from the shore supply and
had to run the generator, which is A. noisy and B. costs us money for
the diesel.
We had to find a more efficient way of
lighting the vessel, looking at all the new buildings in Liverpool, they
were using 110v fluorescent lights as temporary lighting, so a search on
the internet soon found a company that manufactured them.
Cooper
Lighting and Security manufacture a range of lights called Crompton
Tufflite, made from tough GRP and rated at IP65 which means they are
dust and water jet proof, just what we wanted!
I approached the firm and explained our
situation and they very kindly agreed to support our project and donated
10 of their Crompton Tufflite 110v fittings, complete with battery
backup, which means, in the event of a power failure, they provide
sufficient light to enable the compartments to be evacuated safely.
The photo shows me with one of the new
fittings in the lower saloon.
- John Hake |
NOVEMBER 12
A TOUCH OF WIND
On Tuesday 23rd October the weather was just
perfect and with sixteen volunteers in attendance we had enough hands to
move the ship.
The move was needed to allow us access
to the port side belting and involved turning the vessel through 180
degrees. It also allowed us the opportunity to re-position the boat
further along the quayside where the dock wall is of a uniform
height and devoid of obstructions, buildings and so on.
The new location places the vessel
closer to the new workshop/store provided by our hosts United
Utilities.
The weather was crucial as without the
aid of a towing vessel the move needed a little help from nature
along with the co-ordinated efforts of everyone in attendance.
A gentle breeze in the right direction
was all that was required to set the vessel in motion once all but
one rope was let go, so that the power of the wind caused the 'DA'
to pivot around the stern to complete the manoeuvre. I am delighted
to say that all went exactly as planned and the move was completed
without so much as a scratch to the ship. Of course we need to turn
her back the other way before the onset of winter really bites as
the prevailing winds will render our present position very drafty!!
Whether we'll manage that with just
nature's help we shall see, in the meantime some photos of the
'move' courtesy of Colin Brogan...
|
 |
 |
 |
 |
|
The main deck covers are raised to allow the ropes to be handled safely. |
The 'pivot' in progress |
Nearly 'round, a bow rope is already
ashore and another made ready.
|
All secure |
 |
Can anyone spot the 'deliberate
mistake'? (left)
That's it, nobody thought to open the
cover on the prom.deck for the gangway!! (Soon sorted!!)
|
|
Thursday 25th saw us hosting a visit
from Mr Fred Redmond, Chief Engineer of the preserved steam tug 'Challenge'
which is presently awaiting some essential restoration
work herself. Fred was accompanied by 'DAPS' Member, Bob Adam of
the tug 'Kerne'
who you'll have seen recently inside the 'DA's boiler again
assisting the 'Challenge'
team with their research. Despite the distance apart (Challenge
is in Shoreham, Hants.) this is not the first time we've liased
with them, having already had a visit from Bob Long another of their
team. Above all the preservation of historic vessels comprises
a relatively small group in the UK, despite all claims of our
national heritage as 'a seafaring nation' so that helping one
another is vitally important, in fact it's essential if all but a
handful of ships are to survive.
BELTING ALONG
I mentioned that the main reason for
turning the vessel around was to gain access to the port side so
that we could carry on with the removal of the wood belting. You'll
recall that we completed the starboard side and stern some while
back, so we were anxious to complete the work before the winter
gales made the job too hazardous.
The idea is to remove all the old rotten
belting to allow examination of the steel beneath, thereby
establishing its condition and whether or not repairs or replacement
will be needed as we progress towards the major bid application. The
removal of the old waterlogged belting would also improve the
vessel's trim as since removing the starboard wood sections the 'DA'
had assumed quite a pronounced port list!! Accordingly the
volunteers wasted no time in setting about the removal job and
displayed an expertise gained from the earlier work. The sections
literally flew off by comparison with the earlier efforts (probably
thanks to my staying on deck this time!!) and within about three
working parties the job was done! The ship now rides on a noticeably
more even keel, but the wood alas is beyond salvage. Estimates vary
but we expect it must be over fifty years since the belting was last
replaced and of course it received little or no attention in the
last twenty. As a result the timbers are in an advanced state of
decay and even hopes of producing some 'souvenir' items from them
looks distinctly unlikely. If we do manage, you'll be kept informed
on this web-site, so keep
checking.
_small.jpg)
Still
at it (another day!) This time Kevin (nearest camera) and Graham
Dean continue the hard work. (left) [Neil Marsden]
Pete
Murray (nearest camera) and Kevin Lytton get stuck in on the
belting. (right) [Colin Brogan]
_small.jpg)
A 'cropped' circle? In the process
of clearing away the belting a number of these circular marks were
discovered in the hull. We believe these marks indicate the location
of the rounded pads which supported the side fenders over the
belting in earlier times, see historic photos. Maybe a good time to
consider restoring them perhaps? [Neil Marsden]
STEAMING SWEDES
As I mentioned earlier there is much to
be said for the camaraderie to be enjoyed by building links with
like minded groups, not least the mutual benefit to be derived by
exchanging ideas and experiences. You may recall that some time ago
we received a visit from Leigh Doeg from Melbourne, Australia whilst
he was visiting a selection of European steam vessels on one of his
annual trips. I am now delighted to say that it seems not only did
Leigh join 'DAPS' during his visit but also recommended us to some
friends in Sweden.
Accordingly on Thursday last, we
received a visit from a group of five gentlemen from Sweden,
definitely taking a 'busman's holiday' in the UK, for they are all
fully involved in the operation and/or restoration of some fine
steamers back home in Stockholm. The party comprised Tom Smith,
Chief Engineer of the steamer 'Saltsjön'
(yes Tom is from Stockholm!!) Niklas Schölin, Technical coordinator
Blidösundsbolaget, Johan Bäckström, Master s/s
'Blidösund 'and m/s 'Sjöbris',
Matias Aronsson, deckhand
Blidösundsbolaget and last but by no means least Krister Strandell,
of Stockholm’s Ångkol and owner of the steam tug
'Stockvik' ( ex St Canute ).
As you will see from the
following links, these guys really have 'got the tee shirt' when it
comes to restoring and operating steam vessels. I'm glad to say they
did seem to approve of our activities, but sadly their visit was all
too short and it was soon time to leave as darkness overtook
proceedings. Krister loaned me a CD-Rom of his work restoring
'Stockvik' which I remember well as an
exhibit (static) at Exeter Museum in the late 60's. As you'll see
from the website Krister. assisted by Johan and others actually
sailed her from Exeter to Sweden, where the restoration is well
underway!! It's certainly inspiring stuff and dare I say a great
motivation for us too. They also brought with them a small pamphlet
published annually in Sweden which lists all the operating,
passenger carrying steamers in the country, I counted at least 26
capable of carrying over 50 passengers and no less than ten
operating around Stockholm alone, most of which carry over 200!
Please take a look at
the websites for the three vessels represented by our guests;
www.blidosundbogalet.se;
www.saltsjon.nu and
www.stockvik.tk
and of course if you happen to be in Stockholm on your
travels, well...............
I'm
afraid quite a poor photograph of our Swedish Guests (as ever you
can never take too many photos!!) L to R,
Matias,Krister,Tom, Niklas and Johan. [Neil Marsden]
Earlier the same day we welcomed a
return visit from Graham Lee of the Hunslet Steam Co. You may recall
I reported our visit to Graham's works and railway at Statfold Barn,
near Tamworth in the October 2nd update. During our visit we
discussed some of the challenges we face in restoring some of our
engine parts due to the size restriction of some machining
facilities, Graham kindly agreed to come along and take a look for
himself. True to his word Graham joined us on Thursday and despite
having a very busy schedule, stayed for a spot of lunch and probably
much longer than he intended. Importantly it may be that Graham's
company has the necessary equipment and expertise that we need,
he certainly seemed to enjoy the visit and that's always a
good start!
Graham
Lee (seated) discusses 'olde tyme engineering' with a couple of our
'Olde Tyme Engineers'! L. Graham Dean and R.John Deakin. [Neil
Marsden].
More news soon!!
|
|
A very brief report this week on the
subject of the recent AGM and 'Open Day' aboard the 'DA' at Sandon
Dock, Liverpool.
Well first off I'm delighted to
report that despite the last minute change of date and the enhanced
security measures in place at Sandon Dock, the open day aboard was
very well attended. Somewhere of the order of twenty volunteers
attended on the day to cover the visit, stewarding guests to the
boat, giving tours, staffing the shop and the refreshments stall
etc. Our gate crew counted in over fifty visitors so that the open
day was very well supported in the circumstances and once again it
was nice to see some old familiar faces and not a few new ones too.
The AGM followed later at the
Maritime Museum, though with fewer in attendance and despite a very
interesting presentation by some of the council, word filtered
through that the venue was considered by some a little off-putting.
I understand this is mainly due to the developments ongoing in the
area of the Albert Dock at the present time. One of the main
complaints seems to relate to the parking situation, the new
multi-storey, as yet incomplete, car park being the principal
concern.
The fact it's neither conveniently
located to the Albert Dock nor cheap being the principal
complaints. The distance is particularly problematic for those with
limited mobility. So the hunt is on for an alternative venue for our
next meeting. Wherever we do decide, remember it's probably a good
idea to consider car pooling, the dock is not well served by public
transport, whereas obviously the city centre is.
It may well be that a suitably
located 'hostelry' might be considered for future meetings in which
case the opportunity for some social discourse may be possible for
those wishing to chat a little later. Naturally we would commend a
teetotal driver in all pooling arrangements if this becomes an
option!

Some of the 'DAPS' ladies take charge
of the refreshment stall.
John
Broomby (L) and Treasurer Alan Hughes 'Urn their keep!'
Guests
of all shapes and sizes in attendance with familiar faces and new
ones too!
|
|
A 'GUESTBOOK' -
GUEST
Readers will recall I have mentioned
previously one of our 'Guestbook' contributors Doug Livens from
Hamilton, Ontario, in Canada. He remembers the 'Daniel Adamson' many
years ago and has fond memories. He is also involved in a
restoration project himself and has kindly forwarded some photos to
me, which I'm sure you'll be interested in seeing. The project is to
restore a Westland Lysander to flying condition, which by the looks
of things is well advanced. Doug obtained his pilot's licence on
moving to Canada some years ago and I'm sure he's up there at the
front of the queue to get this wonderful old aircraft by in the air.
Good luck to Doug and everyone involved!
A proud day, Doug is pictured with the fire extinguisher adjacent to
the aircraft as the final preparations are made to fire up the
engine for it's first run after overhaul. Note the size of those
concrete 'chocks' under the wheels, no wonder with 880HP about to be
unleashed!! That's about an extra 300HP over the 'Danny's' two
engines combined!! The test was a success!
A
scene a little less dramatic as Doug applies a brushful of 'TLC' to
those distinctive 'Lysander' wheel 'spats'
I'm sure everyone will agree, it's a
fantastic project and one to be very proud of. I think I speak for
everyone here, that we know how you feel and what a great sense of
achievement we all achieve with every step we make.
That's all this week folks, but we'll
be back soon with more news as we get it.
- Neil Marsden
|
|
WEB
MASTER CHANGE OF ADDRESS
Your web master and Tow Line
editor will shortly be moving to a new address. Please update you
records accordingly my new address is:
John H. Luxton
10 Gorsebank Road
Liverpool L18 1HL
Merseyside
Whilst I will not be moving
until approximately mid November this address can now be used for all
correspondence. |
|
AGM - SUNDAY OCTOBER 07
DAPS Members will have access to the
DANIEL ADAMSON on Sunday morning at her berth at Sandon Dock.
Access will be through the United
Utilities gate. This is near the Sandon Dock Treatment Works which is located further north along the Dock Road
than the Salisbury Dock Entrance.
DAPS Representatives will be on the
gate from 10:30 to welcome members and direct them to the vessel.
Please note this open morning is for
Members Only - the general public are not admitted.
The AGM will be held at 14:00 At the
Merseyside Maritime Museum, Albert Dock. |
OCTOBER 02
KEEPING ON TRACK
Sometimes it's a little difficult to
dream up a suitable opening heading for these updates, but I think
as you will see from the following photographs and captions, this
week's title sums up our activities quite well.
As anyone involved in a restoration
project will have discovered, identifying competent people to do the
work is a major part of the exercise. Firstly this starts with
gathering together a willing and able group of volunteers, firstly
someone to organise everything and then others to actually roll up
their shirt-sleeves and do all manner of jobs, free, gratis and for
nothing. In this respect I am confident in saying that we have
developed a very competent team with a wide range of skills. Over
time a growing number of members have joined, bringing with them a
level of professional competence which I believe places 'D.A.P.S.'
in a most fortunate position. This not only allows us to tackle
quite specialised tasks ourselves, but the ability to carry out
effective surveys and assessment of the work required to restore the
vessel, often without recourse to engaging specialist consultants
for each and every aspect of the project. In addition our 'in-house'
(should that be 'aboard-ship'?) Technical Advisory Group are able to
discuss proposals, produce plans and draw up detailed specifications
for work to be carried out by specialist contractors. Indeed working
in conjunction with statutory bodies such as the MCA at the planning
stage like this, ensures that our proposals are compliant with all
relevant legislation applicable to a vessel of this age.
It would be foolhardy indeed to
undertake a project of this nature, much less commit substantial
funds to work not sanctioned by the relevant authorities. By the
same token the society is fully aware of the responsibility we have
for retaining wherever possible the 'heritage value' of the ship,
while at all times placing the health and safety of crew and
passengers uppermost in our minds.
An important consideration involves
identifying the extent of work needed to fully restore the vessel
and which we cannot properly perform ourselves. Naturally the full
overhaul and repair of the boiler springs readily to mind, but there
is a great deal more besides. There are literally hundreds of tasks
which require specialised skills, complex machining procedures and
the need of experienced craftsmen which we lack. In many cases it is
a major task to identify people today actually capable of carrying
out this work and we make every effort to identify these skills
wherever and whenever possible.
A recent case in point involved some
of our members visiting the site of the Statfold Barn Railway near
Tamworth Staffs. Here the successors to the Hunslet Engine Company
manufacture brand new steam locomotives of exceptional quality (see
www.hunsletengine.com) amongst a wide range of industrial and
specialist railway equipment manufactured elsewhere in the group.
The visit coincided with a special 'invitation only' open day held
there recently and allowed an insight into the range and quality of
engineering facilities available. The chance to see some examples of
the locos in operation and others 'in build' provided very clear
evidence of the high level of expertise the company possesses.
Photo
1 Shows our own 'Engine Driver' (Chief Engr.) John
Deakin as a passenger aboard one the railway's restored locomotives.
Last Tuesday the vessel received a
special visit from members of the national Historic Ships Committee
who were visiting Merseyside for a meeting later that day at
Liverpool's Maritime Museum. The meeting was attended by numerous
groups from the region involved in all aspects of maritime
restoration, with DAPS being represented by Chairman Tony Hirst and
Technical Adviser, David Pickup.
Earlier the committee spent the
afternoon aboard 'Daniel Adamson' where Tony Hirst presented an
excellent 'Powerpoint' presentation of the work aboard and the
proposals for the restoration of the vessel. Light refreshments were
provided before the NHSC group took the opportunity to meet several
working party members and took in a full tour of the ship. I for one
felt that the visit went very well and was a most valuable
opportunity for all involved.
Photo
2 Shows L to R (foreground) NHSC's Martin Heighton
(Director) and Dr Robert Prescott (Chairman/Advisory Cttee) with, to
the rear Simon Stephens (Case Officer) with 'DAPS' member John
Broomby. In the background NHSC/HLF Consultant Tim Parr talks with
David Pickup (R) and Mike Williams (back to camera) of DAPS
Earlier
the same day we engaged in a little inter-society co-operation as
shown in Photo 3 which depicts Bob
Adam of the Steam Tug 'Kerne' also
a DAPS Member inside the 'DA's boiler. Bob was taking photographs
and measurements of our boiler to assist the volunteers from the
Steam Tug 'Challenge' with their
ongoing boiler repairs. I am always delighted when we can link up
with fellow enthusiasts and help each other, we are
especially looking forward to the day when we can rejoin the all too
small number of preserved steamships operating in the UK!
Finally a typical story of work
aboard 'Daniel Adamson' entitled,
'One Valve, Two Men, Three Weeks'
The accompanying photos show just how
difficult some 'routine' jobs can be at times. Basically Phil Booth
and John Hake are two of our regular 'Saturday Crowd' they are
restricted to Saturday working parties like most of our weekend
volunteers who actually have a proper job in the week! So it was
that three weekends ago they were tasked with removing the fore-peak
tank isolating valve for overhaul. It very soon became clear that
'overhaul' was a rather optimistic proposal, the valve was in very
poor shape and badly corroded. The location of the valve in the
narrow confines of the forepeak tank meant that dismantling it would
be no easy matter, but they certainly tried their best. Despite
every care it soon became apparent that the valve was beyond repair
and that it's removal to allow replacement was the next step. Such
was the condition of the piece that delicate precision instruments
like spanners were of no use and more basic implements would be
needed. Increasingly larger hammers were selected although in the
restricted space available these proved less effective than had been
hoped. This was another job for 'the whizzer' or more correctly an
angle grinder with cutting disc attached. John and Phil took turns
attacking the resistant valve from every angle in the vain hope of
extricating it with minimal damage, but to no avail. This little
gate valve was not coming without a fight! For two working parties
it resisted their combined efforts, but finally on the afternoon of
the third it finally succumbed, piece by piece in fact, not so much
resembling a modest valve but more akin to an archaelogical relic
from a 'Time Team' dig!! The point of my tale?
Well when people ask why does it take so
long to do such and such? Then apart from the obvious that some jobs
cost a great deal of money to pay for, others take a great deal
of time and effort, that said it wouldn't be half so interesting or
so much fun if it was easy!!
Photo
4 The workplace...no down the hole in the floor!

Photo 5
The valve, that's the one in the upper part of the photo, very much
beyond 'overhaul'!
Photo
6 Phil Booth in action with the 'whizzer'
Photo
7 Phil emerging from the forepeak for a breather
Photo
8 The Victors and the Vanquished, Phil and John
with the spoils of battle!!
|
|
SEPTEMBER 20
A Busy Week!
Unless this is your first visit to
this web-site, most readers will know that we try to maintain
updates on progress with the project on a regular basis.
I for one feel strongly that a
'dormant' web-site can and often does imply little activity with the
actual project the site represents, for that reason I am delighted
that in over three and a half years since we started, rarely has
there been an occasion when we've struggled to report something
happening.
This week is no exception and we have
been even busier than usual with three working parties as well as a
three day heritage show to contend with!
Not only was last Tuesday a regular
working party day, but it also marked the occasion of another visit
to the boat by the Mayor and Mayoress of Halton and Council Staff.
This is the third such visit we have received from the Mayor and is
in my opinion a very clear indication of the genuinely high level of
support the project enjoys from Halton BC. On this occasion we were
delighted to welcome the new Mayor and Mayoress of the Borough,
namely Councillors Mike Hodgkinson and his wife Mrs Kathy Hodgkinson,
together with old friends Agnes Smith and Councillor Steff Nelson.
It was very evident that the new
Mayor and Mayoress were every bit as interested in the project as
their predecessors and took time to visit all parts of the ship,
including the engine and boiler rooms during their visit!
Once again Phil Janion provided an
excellent buffet which was enjoyed by all and allowed us to
personally express our appreciation of the vision and support
provided by Halton.
Photo
1 (J.Broomby) His Worship the Mayor, Councillor
Mike Hodgkinson chats to founder Dan Cross and Mike Williams, in the
foreground Doug Hall lends a hand with
a welcome 'brew'
Photo 2 (J.Broomby)
Mayoress, Kathy Hodgkinson chats with DAPS Treasurer,
Alan Hughes
Photo
3 (J.Broomby) The FULL tour! Here the Mayor and
Mayoress visit the boiler room with Chief Engineer, John Deakin.
Photo 4 (D.Cross)
The Mayor is presented with a
short DVD showing ongoing work aboard ship by Colin Leonard.
(Pictured L to R Agnes Smith,Councillors Steff Nelson, Kathy
Hodgkinson and Mike Hodgkinson of Halton BC together with John
Deakin, Colin Leonard oh and me from 'DAPS')
The day marked another milestone as
our working party hours passed the 25,000 hour figure, quite a
healthy indicator of just how much effort is going into this project
by our volunteers and of course this does not include all the hours
'backstage' in the planning and organisation of everything!!
The regular Thursday working party
was followed immediately by the opening day of an important heritage
event marking the 800th Anniversary of Liverpool's Charter in 1207.
'The Big History Show' was a three
day event staged within Liverpool's famous St. George's Hall,
recently itself the subject of a major restoration.
The event 'showcased' a wide variety of
local as well as regional heritage and historical groups, while
outdoors further entertainment was provided by historic vehicle
displays and live musical performances. Fortunately the weather was
generally kind for the whole event and attendances were very
encouraging. Once again the 'DAPS' stand was staffed each day by
three volunteers, yet it was still possible to hold a Saturday
working party as well so that no time was lost on the project
itself.
It was perhaps significant that the
'Daniel Adamson Preservation Society' was the only group in
attendance representing an ongoing, Merseyside based, Maritime
Heritage project, a fact I believe did not pass unnoticed by many
visiting the show. We certainly enjoyed considerable interest and I
believe have definitely raised the profile of the project locally at
least.
As ever it is appropriate to thank
everyone who took part in events over this busy period, be they
working party volunteers or those who gave their time at the show,
it's exactly this level of commitment which counts.
In closing, in my last update I
invited readers to add a 'Guestbook' entry on the site and I extend
the invitation to do so once more, it is most valuable in assessing
opinion and interest, so don't be shy, we can take it!
One 'Guest' did respond and in very
complimentary terms too, I confess I blushed, but it's always nice
to receive a compliment! Actually I contacted the writer, Doug
Livens who's now living in the Canada, although an ex-pat with fond
childhood memories of the 'Daniel Adamson'
a long time ago.
It's great that through the site,
news of the project can be read literally anywhere and as has
happened more than once we have linked up with like projects all
over the world which can be very encouraging. In Doug's case he too
is very much involved in a restoration project, but not a maritime
one, in fact he's busily restoring a vintage aircraft to flying
condition, a real classic in my view though often overshadowed by
more well known marques, the Westland Lysander, the aircraft made
famous by its role in delivering and extracting allied agents in
occupied Europe in WWII we certainly wish Doug and his colleagues
every success! See
www.warplane.com
Photo
5 (N.Marsden) The 'DAPS' stand at the 'Big History
Show' staffed by Judith and Alan Hughes, that's two visits this week
by Alan despite his having to travel from Skipton in Yorkshire,
another example of commitment to the project, although I think my
photo may have caught him 'resting' briefly!!
Photo
6 (D.Cross) Another view of the stand now complete
with lights etc. and if I do say so, looking well suited to the
occasion, this view caught on Dan Cross's mobile 'phone.
Lots more news in the pipeline so
please look out for our regular updates to be right up to date with
all that's happening with the project.
|
|
SEPTEMBER 10
Notice: AGM /
Birkenhead Bus & Tram Show
The more 'eagle eyed'
amongst our readers/members having now received the latest edition
of 'The Tow Line' will have spotted
an unfortunate clash of dates.
Owing to last minute
problems the date of the Society AGM has now be changed to
Sunday 7th October 2007, this was also the date
we had hoped to attend the ever popular 'Birkenhead Bus
& Tram Show' held annually at the Pacific Road buildings
in Birkenhead.
Obviously the AGM
must take precedence and accordingly we are unable to attend the
Birkenhead event this year as a result. All is not lost of course as
the DAPS stand/display will be at Liverpool's St.George's Hall for
the 'Big History Show' from Friday 14th to
Sunday 16th September (next weekend in fact!) so please come along
and lend your support, it will be good to meet you.
KEEPING BUSY!
Just a short
update with few words and more pictures this week which I expect
may make a pleasant change for some!!
I do hope that
regular visitors will have viewed most if not all of the content of
the site which we have continually striven to keep 'live and active'
with frequent updates since it first came on line in 2004.
For new and
more recent visitors I hope you will take a little time to look back
over the years and will I hope see what progress we have really made
from our first hesitant beginnings. There's a lot of information in
here and I hope you'll find it interesting, if you do please add a
line on our 'Guest Book' as it's nice to see who's out there keeping
an eye on our progress.
Okay
then, to illustrate what I'm saying take a look at the first photo
(left) This shows the steering quadrant as it looked back in 2004
when the vessel was made ready for the tow to Liverpool at the very
beginning of the project...
The
photograph on the right Shows the scene three weeks ago
when work got underway to chip and scale the steelwork, under the
quadrant itself. Here Pete Murray (L) and Bill Rathbone make a start
on the chipping.
The
quadrant itself is seen on the left, now removed from the rudder
shaft/tiller arm. Undoubtedly it has been many years since it was
last removed and I can assure you it didn't 'give up' without a
struggle!! Much hammering and the use of the largest steel wedge in
Wally Graham's comprehensive collection finally won the day. As can
be seen it's suffered some corrosion damage, but is certainly good
enough to allow some 'reverse engineering' to be applied and new
parts made.
Here
Nigel Farrell gets to work with the needle gun, it's looking much
better already!
Ready
for the NDT testing (left) before treating with 'Rustroy' and
painting. Initial readings give an average plate thickness of 7.5mm
which is pretty good in the circumstances and barring any unforeseen
problems should be adequate for purpose.
By
contrast the photo (right) was received from Dave Skinner in New
Zealand who by coincidence is restoring a Robinson engine-room
(repeater) telegraph, very similar to those installed in the
'DA' On my first viewing I didn't realise that Dave's machine
was in fact slightly more complete than those parts remaining
aboard 'Daniel Adamson', but then when the bell/gong is removed
from the spigot.....
I ndeed
the major components are still there (left) and I'm delighted to
say, as so to are the ones on the "Danny" (right).
By
comparison it seems we lack only the bells and of course as in
David's case, the dial faces, pointers and brass bezels to
complete these essential items, the majority of the components
have miraculously survived intact.
We are
pretty confident that we can replace the missing items both here
in the UK and if needs be those in New Zealand too. IF YOU
CAN HELP IN ANYWAY PLEASE GET IN TOUCH
Regular
weekend volunteer Steve Greenhalgh (one of youngest) helping
with the chipping on the aft deck (right) while the last
photograph shows
one
of our more 'senior' volunteers, Jim Ellis, (left) still a
very active and innovative participant, here re-cutting
valve seats in the GS pump valve chest using his own
improvised cutting tool. It works perfectly, just like Jim!!
There's
lots more to show you, but we don't want to spoil the AGM for
you, or our stand at the 'Big History Show' so make sure you
come along if you can!
|
|
WHAT LIES AHEAD
Work aboard continues very much at a
constant pace and we hope that shortly we will be in a position to
despatch the main engine crankshafts away for repairs.
This is yet another significant step
as we progress toward the full restoration phase. the process will
involve the removal of the crankshafts from the engine-room
(naturally) which will require the use of a mobile crane and
specialist riggers. Once loaded onto a suitable vehicle the
crankshaft will be despatched to the selected contractor who in
liaison with the firm tasked with re-metalling the main and bottom
end bearings will regrind the crankshafts. By this method the wear
and ovality found in the shafts can be made good and the newly
metalled bearings machined to suit. In addition having established
the alignment of the main bearing pockets, the main bearing shells
will be machined true also. In addition the eight eccentrics will be
ground and polished and their respective sheaves machined
accordingly, these in turn will be adjusted to compensate for the
machining process, thereby maintaining the correct length of stroke
to their respective valves. As might be imagined this is a
specialist task and represents a substantial investment of society
funds, but is absolutely essential in ensuring the proper operation
of these two unique engines.
It might be overly optimistic to hope
for an 'as new' result, but we do expect a considerable improvement
in operation since their last major overhaul, which we believe was
over fifty years ago!
Once this work gets underway and we
do need to move the boat to allow access for the lift, we can
continue with other work in and under the engines not normally
possible with the crankshafts in situ. This will mainly involve a
thorough clean and paint job, ready for their return. Hopefully time
will allow for much additional tidying of the engine room space
which does not readily lend itself to mechanical cleaning methods.
At the same time preparations are in
hand as and when the necessary funds are in place to rebuild the
condensers, another major exercise, again with a considerable cost,
but one much reduced overall by the level of volunteer labour
involved. The stripping phase was entirely carried out by our
volunteers, while the rebuild will be as well. The expense arises
from the purchase and in some cases the manufacture of new parts to
complete the job
In a very similar vein the starboard
belting has now been completely removed by our own people and we
merely await access to the port side to complete the task.
A recent tightening of security on
site has brought about some delays whilst access issues are
resolved. Meanwhile everyone involved is striving to achieve a
positive outcome to the mutual benefit of all, so that hopefully we
can soon pick up the pace once more. It should be said that security
is vitally important and these new measures are as much to our
benefit as anyone else. We do hope the usual 'open day' for the AGM
will be organised in good time, taking into account the improved
security level and notices will accompany the forthcoming 'Towline'
shortly.
Perhaps it is relevant to
stress that (current/valid) Membership Cards should be carried to
allow access at the 'open day'
The heading poses the question of
what lies ahead? It being my intention to give an indication of
where we are upto and where we are going.
Apart from the work aboard a great
deal of planning is ongoing, this is largely the remit of our own
Technical Advisory Group and takes into account general requirements
and many other issues, some of which impact on several aspects of
the restoration.
Probably the most important point to
stress is that the restoration is a 'restoration to full operation'
and I believe I am correct in saying that at the present time no
other similar project exists in the UK, that is to say that the
restored vessel will be capable of carrying passengers and as such
hopefully 'self sustaining' thereafter.
In the majority of maritime
restoration projects the selected vessel is either restored to a
static role and potentially open to the public or in some cases
restored to operation but constrained by capacity restrictions to
carry a crew and at best a handful of guests. The 'Daniel Adamson'
is to be restored to her Class V passenger capacity of 100 plus
crew. The certificate is granted only if stringent safety measures
set by the MCA are implemented and the vessel is limited to
operation in designated waters only.
While this may sound restrictive, we
are fortunate that a considerable area of waterways are accessible
to the vessel in the region and of course the vessel can also
provide an excellent static facility too, whereby numbers would be
less limited. Passenger numbers would also be determined by the
duration/distance of the trips involved and naturally dependent on
tidal and weather conditions.
Although we have a clear idea of
where, how and when we will be able to operate and a fair idea of
overall operating costs, as might be expected certain ground rules
naturally require that detailed reports are drawn up beforehand.
Whether this is a legacy of 'the dome' or just commonsense it
matters not, the fact is they must be provided and as you may well
guess they don't come cheap!
Ahead of this we must anticipate our
general operating requirements, we must also consider the historical
integrity of the vessel, yet we must comply as far as possible with
the requirements laid down by the MCA. The vessel's age and design
provides some leeway in this area which would certainly not be the
case for a new build vessel or replica. Nevertheless a sensible and
responsible approach must be adopted and a balance achieved if at
all possible. It is fair to say that a static, historically accurate
vessel permanently moored in a museum is a much more straightforward
project. So compromise there must be, but this cannot apply to
safety which naturally must come above all.
So in service the vessel will carry
lifesaving equipment compliant with today's laws, communication
systems and sanitary arrangements never needed before. Health and
safety issues must be addressed and if practical access improved.
This must then be combined with retaining the vessel's historical
integrity and at the same time providing improved facilities for
both passengers and crew! So at a glance you can see what we're
dealing with here. Add to that the need for security in today's
'enlightened times' and you will understand the need for some
compromises.
In general terms we would like to see
the vessel's external appearance approximate to what it was in the
1930's, structurally it would not be practical or perhaps even
desirable to depict the vessel in an earlier guise. Of course the
purist would point out that the vessel had an open bridge until at
least 1949, but of course they also had National Service, hard
labour and capital punishment back then too, so an open bridge
though perhaps a little uncomfortable was more likely to retain its
contents in those days. So in the unlikely event of the resumption
of those days, we must have an enclosed (alarmed) wheelhouse, thus
representing the early 1950's look, which in fairness represents the
vessel in her mid-life and if done well a rather pleasing profile
should result.
In the main the saloons, prom. deck,
wheelhouse, boiler and engine-rooms will be restored to their
'original' appearance. Importantly the motive power of the vessel
will be wholly original and unchanged. Some modifications to bilge
water and sanitary arrangements will require the installation of
holding tanks, but it is hoped that these will be designed in such a
way as to have very little visual impact (and hopefully no impact on
the other senses either!!)
All compartments will incorporate
modern insulation and coatings to reduce degradation by corrosion
and condensation etc. while fire/smoke detection systems will be
incorporated where practical, the boiler room naturally being a
little difficult in this regard. Wherever possible the use of these
materials will be 'contemporary' in general appearance to the
original and insulation installed behind panelling.
Elsewhere minor modifications will be
needed or where these are considered desirable. For example it is
hoped that some flexibility can be incorporated in the area of crew
accommodation, the original layout provided berths for seven crew,
whereas it is hoped to provide some extra berths to allow the option
of carrying additional personnel.
The days of only cold wash water and
an old oil drum for a shower have gone, hot water will be provided
and by a modest enlargement of the aft deck houses a crew shower too
on the port side, while the enlarged starboard deck house will
incorporate much improved catering facilities. The deckhouse height
will be slightly increased as well, providing greater space/headroom
internally and at the same time reducing the risk of head injury
from the beams which cross the deck between the two houses.
In the ship's later service these
beams supported a number of liferafts, although their original
purpose was as 'tow bows' to keep ropes clear of the deck. As things
stand these are far too low for safety as I know only too well and
have proven the value of wearing a safety helmet on many
occasions. In passenger operation it is far better to raise these to
a safe height rather than risk injury to anyone.
Many of these improvements will
inevitably add to the ship's electrical load and will exceed the
capacity of the existing steam driven generator. Accordingly careful
consideration is being given to the siting of a suitable, 'silent'
type diesel generator capable of providing ample power for all our
perceived requirements. There are several advantages to this
proposal not least of which is that power can be provided at any
time, anywhere irrespective of whether the vessel is in steam or
not..
Of course this all sounds very simple
jotted down in a few lines on paper, translating it all into a fully
costed, approved plan is another story, but we feel confident that
we are making steady progress to this end.
I have no doubt this particular
aspect of the planning stage will be gone into greater detail at our
forthcoming AGM, so don't miss it or your opportunity to put any
questions you may wish about the project there.
|
AUGUST 14
LOCAL INTEREST &
LOCAL SUPPORT
It is now a week or two
since my last update, but I can assure you a lot has been happening in
the meantime.
Aboard, or rather
over the side, the removal of the belting has continued to the
extent that all the starboard side belting has now been removed
together with the doubled area at the stern. This has taken several
teams of two men over 130 hours to complete, not to mention the
consumption of a dozen or more 9" cutting discs, used to cut out the
securing bolts. The result is very satisfying as this will not only
save time and expense later but allows us access to examine the
underlying steel of the hull and the belting channel material as
well. NDT tests at selected points along the hull indicate very
little significant corrosion to the hull sides under the belting,
but as might be expected, quite severe deterioration to the lower
portion of channel section in which the wood belting has sat for a
great many years. No doubt the decaying wood has retained much
moisture over the years which will have accelerated the process in
this area. The indications are that this section of 'angle iron' has
been replaced previously, no doubt due to the same problem. The
upper section, by contrast appears almost perfect and may well be
original as it is still attached by rivets, while the lower section
had been welded in place. As things stand it would seem that only
this lower section will require new steel when the restoration gets
underway, so all things considered the news is quite good.
Elsewhere the volunteers have been
preparing the engineroom ladders and gratings for removal in order
to facilitate the extraction of both main engine crankshafts ashore
for machining.As
reported previously the bearings are already in the process of being
re-metalled and will be machined in due course to ensure an accurate
fit with their respective crankshafts. A number of competent
contractors have been approached to submit tenders for this work and
we will shortly be selecting the most capable to carry out the work.
Of course lifting and transporting the two shafts and replacing them
afterward adds considerably to the overall cost of this exercise,
but for safety and peace of mind it will be money well spent. There
are some tasks best left to the professionals and this is no
exception.
As you might appreciate this is quite
a major step towards the restoration and I am delighted to say that
we are in a position to proceed with this element of the project in
advance of our major bid application, using funds raised elsewhere.
It is proposed that the repairs to
the two main engines will form a separate, independent element of
the overall project, thus maintaining the impetus of the project and
utilising the skills of our own volunteer workforce at the same
time.
I should stress that our volunteers
are well qualified to carry out much of this work, having a combined
level of experience in the operation and maintenance of marine steam
reciprocating engines unlikely to be bettered anywhere today. With
this team, working in close cooperation with professional
specialists we are confident of a first class outcome and a
considerable cost saving overall. Added benefits include an intimate
personal knowledge of every component of the engines, their
condition, strengths and potential weaknesses, so ensuring that a
well planned maintenance regime can be developed from the outset.
Treating this element of the
restoration apart from the main bid may also assist in keeping the
overall budget within reasonable limits and assist with the major
bid itself.
IN THE NEWS?
Well not exactly, but perhaps on the
radio again soon!
Apart from the web-site and our
quarterly magazine, we do try and keep the wider public aware of our
existence by any means possible, this includes attending rallies and
events, press releases to local and national newspapers, magazines
and so on.
As some readers will know the 'DA'
has featured on television with appearances on BBC North West
Tonight and Granada's 'Locks and Quays' which thanks to the digital
channels has extended to a much wider audience with repeats across
the UK and beyond. We soon hope to announce the imminent release of
another 'TV' short scheduled for release in the coming months, but
more on that another time.
Local radio, particulary BBC Radio
Merseyside have featured the project a number of times thanks to the
efforts of Member Stuart Wood, presenter Roger Phillips and others,
so that I am delighted to report that last Tuesday in response to an
invitation to come down and meet us, BBC Radio Merseyside's 'A' Team
researcher Harriet Whitehead did just that, brought a camera, a tape
recorder and spent an hour or two chatting to various members of the
'crew' .
The
idea is to produce a series of short interviews to accompany on line
articles on the BBC's local web-site, so keep a look out.
The photo shows BBC Radio
Merseyside's Harriet Whitehead during her visit to the boat (Photo
Neil Marsden)
and finally
GREAT NEWS!!!
HALTON BOROUGH
COUNCIL CONTINUE THEIR SUPPORT!!
Literally fresh off the press today,
Monday 13th August, we were notified that our great supporters
Halton Borough Council have generously awarded the Daniel Adamson
Preservation Society another grant of £7,500!!
This really is fantastic news and
could not have come at a better time, combining with other important
awards to progress the vital engine restoration almost immediately!
Halton have over the last two years
donated almost £15,000 to the project, which is itself a fantastic
contribution. Not only that, it demonstrates in no uncertain terms
Halton Council's faith in the project and what it represents to the
area.
We cannot thank all those who
share our vision but in particular we should like to acknowledge the
unstinting support of Agnes Smith and Stef Nelson. Thank you.....
|
|
JULY 18
A BELTING DAY!
In view of the recent weather the
title might appear misleading, we have certainly had our fair share
of rain, though fortunately have escaped the flooding experienced by
others no quite so lucky. Perhaps it is just as well that our
project involves a boat in the circumstances!
The weather of course has had an
impact on the work we've been able to carry out, but not stopped it
at all. A lot of work now involves planning, not just the schedule
of work but all manner of details needed so that we leave nothing to
chance. Some quite major decisions need to be addressed and as you
can imagine reaching agreement on everything is a daunting
task. Perhaps it is sufficient to say that the old adage 'you
can please some of the people
some of the time....' was never more true
than on a project like this, but we are making progress as we must
if we are to achieve our goal.
As mentioned previously the main
engines are being stripped down, the main and bottom end bearings
together with the thrust pads have gone away to be re-metalled,
while we are presently negotiating tenders for the re-grinding of
the two crankshafts. Some of the new castings for the condensers
have now been completed and the next phase is to have these machined
and re-fitted. As the budget allows we then hope to rebuild the
condensers ourselves thereby saving a considerable sum in labour
costs in the process. Of course as we check more engine parts, we
discover more work is required. This is not surprising when the fact
that the engines are now 104 years old is taken into account. The
vital object of the exercise is that the engines are fully restored,
not merely 'patched up', so that it is not sufficient to ensure that
all the major bearings are refurbished, but that smaller equally
important components are given equal attention. Wherever possible
the work is carried out by our volunteers, but when this is beyond
our capabilities then a suitable contractor must be sought and the
work put out to tender. This is particularly so when a new
replacement item is needed.
Volunteer Graham Dean recently spent
a day trawling local archives regarding the engine builders, John
Jones & Sons. Amazingly it turns out that their premises were
located in Cotton Street, Liverpool, just a few hundred yards from
our old berth in Salisbury Dock, sadly they are long gone and no
doubt any spares too, so it's a case of making new ones as and when
we need them. Perhaps it is just as well that Graham is heavily
involved in that process too!
Our
first photo this week shows Volunteer Jim Ellis working on one of
the main engine air pump rocker arm bearing shells (try saying that
when you've had a drink!)
Jim served his time as an engineer
before becoming a trainee bomber pilot in WWII. He later returned to
engineering and has spent a very full life working around the world
in a most varied career. His experience is invaluable to the project
and as can be seen from the photo he still likes nothing better than
to get his hands dirty!
When not putting in a day's work
aboard the 'DA' Jim is happiest carrying out 'odd jobs' at home,
for example re-wiring his house, or carrying out major
servicing tasks on his car. I hope I'll live to be as active as Jim,
in fact I'll be happy just to live to Jim's age. He is an
inspiration and truly deserving of the title, a gentleman.
Our
next photo shows two more 'residents' of the 'Daniel Adamson
Twilight Time Rest Home' in fact none other than Chief Engineer John
Deakin and of course another regular volunteer Wally Graham
(actually only a slip of lad really!) The photo shows the boys about
to test the starboard main engine, steam/hydraulic reversing engine.
The machine has been connected to an
air line and they are about to check it's satisfactory operation
following cleaning and overhaul. I am pleased to report that the
test was a complete success and the engine worked perfectly first
and every time. A brilliant result after over twenty years! (External
Link to YouTube hosted Film Clip)
I do apologise for my rather
'flippant' and decidedly 'ageist' remarks, but the fact of the
matter is, that often when we're attending rallies, the stand is
visited by individuals who having expressed an interest in the
project state that 'they are far too old' to get involved!
In the majority of such cases they are a good deal younger than some
of our most regular and active volunteers! I guess the phrase
'your as old as you feel' is most fitting. True not everyone is
physically capable of playing an active role, but that shouldn't
stop them joining the society. As for those who do get involved I
think all would agree that whatever the weather, it beats sitting in
front of the TV planning your funeral!
Come retirement everyone wants to
give you a clock!! The workmates, the TV ads and so on, just when
you don't care what time it is, much less want to sit watching one
ticking away, so ask for a boilersuit, a hard hat and some 'toe
'tectors' instead or whatever takes your fancy. Do something you
always wanted to do, put those skills you've learned to good use and
above all have fun. A project such as this, is every bit as much
about the people who make it happen, whatever their role as well as
saving an important piece of history.
So
at last to that 'belting day'. Well the sun did shine last Tuesday,
there was hardly a breath of wind and conditions were at long last
perfect to attack the rubbing strake/belting on the starboard side
of the ship. We can't get at the port side for the moment (being
moored port side to) so having arranged to move our neighbour,
Madog to an alternative berth, we
prepared to work over the ships side. Pete Murray and I suitably
attired in appropriate safety gear climbed aboard the
Madog's raft/dive platform which had been
kindly loaned for the occasion and set off to attack the side
belting. The wooden belting is largely rotted away and will require
replacement in the restoration phase, in the meantime we need access
to the steelwork beneath to establish it's condition. The first
stage is to release the protective steel band which runs the full
length of the belting, this acts as a barrier between the wood and
quayside so prolonging the life of the belting material. The steel
band is about 4" wide and 3/8" thick. It is made in assorted lengths
which are butt welded together and secured to the woodwork with
large steel pins. (Actually great big nails, but they do have a
special name which I'm afraid escapes me for the moment, no doubt
the shipwrights out there will remind me!!)
Luckily
most of the 'pins' had worked loose due to the decay of the wood,
but to release the bands we needed to grind through them at the weld
joints, having taken the precaution of attaching several slings to
the piece to be removed!
As might be expected caution was
required when cutting the bands to avoid them springing as they were
released. We soon got the hang of it and ably assisted by all hands
lifting the bands aboard we completed the job almost to the bow,
where the remaining short length remains for the time being,
tantalisingly just out of reach!
The
final photo for this update shows our 'chippies' Gordon Owen (left)
and John Broomby in the process of installing new doors on our
latest 'acquisition'In
fact an unused outbuilding on the United Utilities site which
adjoins our berth. The company have generously allowed us to use the
building as a workshop/store close by the mooring. There is some
work required to clear it out and making it secure. The old doors
were beyond salvaging, but as can be seen the volunteers are already
on the case. You will no doubt have spotted that very useful
beam poking out beyond the door, this extends the full length of the
inside of the building making it ideal for moving heavier items. I
will report more fully on this in due course with updates on our
progress.
Photo Credits 1-4 Colin
Brogan 5 (new store/workshop) Neil Marsden.
- Neil Marsden
|
|
JULY 02
FERRY 'CROSS THE MERSEY?
Apologies to anyone having been
directed to this site via a 'search engine' in the expectation of a
feature on the famous song created by my 'namesake' Gerry Marsden.
I'm sorry to disappoint you as the
article has nothing to do with the song, nor as far as I am aware,
am I directly related to my fellow 'Scouser' other than a shared
surname, oh well, moving on....
The title actually comes about as a
result of the recent discovery of a bundle of original documents, in
what was at one time the archives of The Board of Trade. The
documents dating from 1903, relate to the then 'new' steam vessel
Ralph Brocklebank. The papers
include some drawings, records of registration and the vessel's
'Steam V' (Class 5) passenger certification document. These bear
various official stamps and dates ranging from July to November
1903. In fairness the bulk of the documents provide confirmation of
information which we already knew, but interestingly some valuable
new material. The papers confirm that the vessel, official number
104779 was indeed laid down as yard number 222 and named
Ralph Brocklebank. Her port of registry
is officially confirmed as Chester and that she was designed and
built for the Shropshire Union Railways and Canal Company.
Interestingly one column of the records concerning the material used
for construction provides a choice including, 'wood, composite,
iron or steel' of course the material indicated is given as
steel. The most significant document, providing previously unknown (at
least to us) information is that concerning passenger capacity,
which indicates a figure of 283 passengers, as built! There are a
number of amendments which later adjust this figure to 200 and by
1936 the current figure of 100 passengers.
It is the original figure of 283
which comes as the greatest surprise and which in my humble
submission justifies the description that, as built, the vessel and
her two consorts, Lord Stalbridge
and W.E.Dorrington provided a
'regular ferry service' between Ellesmere Port and Liverpool. Of
course as we know this service was combined with the towage of
barges, so that the term 'tug tender' is fully justified.
If anything the description might be better termed 'tug-ferry'
although I suspect there are purists and others far more
knowledgeable than I who would differ.
Many would say that a 'tender' is/was
a vessel used to convey passengers and their luggage between a
landing place and larger ships lying at anchor offshore. These
vessels might also assist in the towing of vessels as required. In
the main such vessels were often considerably larger than
conventional harbour tugs, used generally for towing duties only.
The Mersey in common with many ports
around the UK operated some fine examples of this type of vessel,
often these were built for the principal steamship companies of the
day, rather than pure towing companies, examples included Cunard's
Skirmisher (1884) White Star Line's
Magnetic (1891) and Canadian
Pacific's Bison (1906)
In addition, Liverpool's Alexandra
Towing Company operated a large number of 'tenders' including
Herald (1907) Flying
Kestrel (1910) and the smaller
Egerton (1911) followed by many more over the
years, virtually until the end of scheduled passenger services from
the port.
It is clear from the numbers built
just how substantial the volume of passenger traffic was at one time
in the port, a scene repeated but probably not surpassed anywhere
else in the UK at the turn of the 20th century.
Today two examples of the type
remain, albeit only in a partially restored/conserved state, Red
Funnel's once steam powered Calshot
(1930) and the recently returned
Nomadic (1911) of White Star Line.
Of course the Mersey Ferries date
back to origins in the middle ages when a cross river 'ferry' was
provided by the monks from Birkenhead Priory. The landing place for
this service and those that followed has provided the town of
Birkenhead with familiar names for a number of districts, Monk's
Ferry, Rock Ferry and New Ferry. In addition ferries services
developed all along the Wirral banks of the Mersey, all serving the
ever expanding port and city of Liverpool. From New Brighton to
Eastham and numerous points between. Over the years vessels were
developed both to convey large numbers of passengers and prior to
the building of the Mersey tunnels an increasing number of vehicles
across the river. Today just three ferries and a similar number of
landing stages remain. Thankfully major investment ensures that this
world famous service continues and hopefully will survive long into
the future.
Of course none of the vessels
operating today or their predecessors were designed to provide a
service other than the conveyance of passengers, certainly no towing
role was envisaged.
So I suppose the question is, what
type of vessel is the Daniel Adamson?
Ferry, tender or tug? She definitely towed other craft. She
definitely conveyed passengers on a regular river crossing. Could
she have carried passengers out to waiting ships anchored in the
river? Well possibly, but probably not, we don't know.
In the magnificent book 'British
Steam Tugs' by P.N.Thomas, a whole chapter (7) is devoted to
and titled, 'Tenders & Passenger Carrying Tugs'. As if to complicate
rather than resolve the issue raised here, the chapter opens with
reference to the first vessel to be credited with the title 'tug'
naming the Industry of 1814 and
stating that she had been built as a 'passenger steamer' in fact a
role she continued as a 'tug' for years afterward!
Perhaps quoting from paragraph 3 of
Chapter 7's opening page may clarify if not resolve the issue, I
will let the reader decide!
In June 1868 the paddle steamer
Walney .....built and designed by McNab &
Co. Greenock made a satisfactory trial trip with a speed of 14.2mph.
She had been built specially for the Furness Railway Co. and was
intended for the passenger traffic at Barrow and was to be used
occasionally for towing; that is the true function of the 'tender'
Without knowing much more about the
services provided by the 'Shropshire Union' 'tenders' say
from timetables, the combined passenger capacity for all three
ships, or whether this number exceeded or was less than the vessels
they replaced, it is difficult to assess their true role. We do know
that they were all designed and built with passenger facilities from
the outset, but that by 1921 demand for their services had ceased
and they were sold.
It would be of great
interest to know some more about the service for which the vessels
were built, so if anyone is able to shed light on this we'd be
delighted to hear from them.
In the meantime the title
'tug-tender' seems the most fitting and whether 'ferry' or not,
there is in the UK at least, no other surviving today which
performed the same role.
RESTORATION PROGRESS
Coming right up to date, what is
happening aboard? The answer is, I'm pleased to report, a great
deal!
Engineroom:-
This is one area of the vessel where we really can make progress
as we prepare for our major funding bid. It is also, along with the
boiler room the heart of the ship and the area where our project
differs most significantly from many others. It differs because the
original 1903 built machinery remains intact, we don't need to
replicate or replace it with some alternative. In the case of the
main engines of course we have two of them, 'mirror images' or so
we once thought of each other, but as we learn all the time they are
not 'identical twins' and there are subtle differences between them.
The fact that we do have two of course means twice the work and
double the cost to restore them.
By the same token having two quite
substantial engines in the same relatively confined space means that
the ship possesses some unique features, notably the fitting of her
remotely operated steam/hydraulic reversing engines. I have waxed
lyrical about these before so I won't dwell on the subject now, save
to say that as far as we know no other examples exist, at least not
performing their intended function in the vessel for which they were
built.
I mention differences with other
projects, some ongoing and one or two proposed, principal of these
is that from the outset it has been our intention to operate the
vessel. The Daniel Adamson would be
a significant historic vessel if she were merely 'preserved' as a
static exhibit, open to the public and providing a glimpse of how
things once were, perhaps with engines slowly turning and powered by
an electric motor for 'effect' of course this would one way of doing
things, but not what we've been working for.
Our goal is and has been from the
outset, to go much further. The engines will once again drive the
ship, the auxiliaries will function as designed and the power to do
this will come from her own coal fired boiler. What is more the
restored ship will join the very small number of preserved vessels
in the UK able to do this and carry the public as passengers as
well.
So it is that the engines and boiler
must be restored to full working order. The boiler is now ready for
the restoration process, a contractor has been identified and the
costs are known. As we expected the cost is substantial and will
require external funding for this and much more besides. That said
we are well advanced in preparing our bid proposals for that
funding. In the meantime the main engines have now been stripped,
their condensers opened up and are being prepared for rebuilding.
Patterns have been made for new tube plates to be cast with the help
of our own pattern maker, Alan Frodsham. Invaluable for his skill as
a pattern maker alone, but equally committed to sourcing much other
valuable material to the project he is just one of our expert team.
The main engine piston rods are
presently ashore being refurbished, while essential new items needed
for their replacement, namely the cylinder neck bushes which had
become worn, are being replaced with the aid of the staff and
students from our linked training establishment TTE in Ellesmere
Port.
The main engine bottom end and main
bearings, along with the thrust pad bearings have now been removed
and have been despatched to a specialist bearing repairer in the
midlands. There the bearings will be re-metalled using state of the
art technology and machined to a fine tolerance preparatory to
refitting them in the vessel. The cost of this work already forms
part of our existing budget.
So that this exercise will have
maximum benefit, it follows that the main engine crankshafts must
receive suitable attention also. To that end we have sought quotes
from a number of specialist firms across the UK capable of carrying
out this work. As may be imagined many engineering firms are well
versed in re-grinding crankshafts of the size to be found in a car
engine, but few are capable of handling a couple each weighing
nearly as much as a car, with dimensions to match! The overall cost
of these essential repairs we hope will not exceed our present funds
and leave us a modest contingency for other urgent matters, however,
it is true to say that pressing on with these major works is a
costly exercise, but I believe illustrates in clear terms our
determination to progress the restoration and our confidence in it's
success.
As ever your support and donations
make this possible, please continue to support us anyway you can,
thank you.
These quite significant steps take
the project beyond the 'conservation' stage and firmly into the
restoration process, soon we hope if funds allow to continue with
the rebuilding of the condensers, more on that later.
The work on the auxiliaries continues
also, as has been reported already Messrs. Dawson Downie Lamont have
generously offered to assist with the overhaul of the boiler room
pumps and a progress update will follow in due course. The
engine-room a | |